EMERALD ISLE, N.C. (WITN) - It has been nearly two years since hurricane Florence washed across the coast of our state. Now one coastal town is ready for the final phase of its renourishment project.

The Carteret County Shore Protection Office says this phase in Emerald Isle will likely start in January or February of 2021.

On Tuesday, the town’s board approved two resolutions to move forward with the project.

Greg Rudolph with the Shore Protection Office says Phase 3 entails a little more than 2 million cubic yards of sand, covering more than 9 miles of beach strand. This goes from the town’s west regional access towards the Bogue Inlet pier.

It’s the final step of rebuilding the county’s shoreline, which was already tested by Hurricane Dorian last year, and more recently, Isaias.

Copyright 2020 WITN. All rights reserved.

Let's block ads! (Why?)



"enter" - Google News
September 13, 2020 at 08:59AM
https://ift.tt/2ZyIad5

Emerald Isle beach renourishment project to enter Phase 3 - WITN
"enter" - Google News
https://ift.tt/2TwxTMf
https://ift.tt/3d6LMHD

Bagikan Berita Ini

0 Response to "Emerald Isle beach renourishment project to enter Phase 3 - WITN"

Post a Comment

Powered by Blogger.